November 27th

  • After a long beam-off period, neutrons returned on November 26th. Experiment was checked out with chlorine --> asymmetry was seen that was consistent with previous measurements.
  • Hydrogen production data is now resuming.

September 25th

  • The hydrogen target is full, cold and converted to para.
  • Facility is down until October 11th (unanticipated mercury target failure).
  • Periodic checks of additive and multiplicative asymmetries (consistent with 0 at <1e-9)
  • Offline analysis is ongoing
    • Parallel determinations of cuts for all asymmetry data
    • Analysis of hydrogen transmission data (for ortho/para fraction determination)